Annual ISO 3 Ultra-Cleanroom Requalification

A 12-inch wafer fab needed annual ISO Class 3 requalification of its lithography bay to safeguard DUV advanced-node yield baselines. SYE completed full-zone particle, ULPA, airborne microbial and ESD verification inside the scheduled shutdown window.

半導體廠超潔淨室驗證
Challenge

Challenge

The photo bay allowed only a 48-hour downtime window requiring three particle counters running in parallel. With several hundred ULPA filters to scan, traditional single-point sweeping was too slow — a grid-based automated scan strategy was required.

Approach

Our Approach

  1. 01

    ISO 14644-1 / IEST RP-CC006 at-rest particle counts and ISO 14644-3 ULPA integrity tests

  2. 02

    0.1 µm particle counter on automated scan fixtures, improving throughput by ~40%

  3. 03

    Airborne microbial sampling via dual-path (settling + impaction) to align CFU readings with process trends

  4. 04

    Delivered full IEST-format report covering FFU performance, ESD and continuous temperature/humidity traces

Outcomes

Outcomes

  • ISO Class 3 compliance maintained
  • Airborne CFU within spec
  • Full IEST RP-CC006 report